On Tuesday, December 8th the construction project to replace the water line on West Cherry Street and Ash Street will begin. The project is estimated to last 45 days. Regular project hours will be Monday – Friday from 7:30 am – 4 pm. During these times, the Southbound lane of West Cherry between Milan and the railroad tracks will be closed. Traffic will be controlled and continue to travel in both directions using the one open lane. Both lanes will be open normally outside of regular work hours. Wenger Excavating has stated their workers will assist in making sure that trash cans are accessible from the street on those particular days. City Utility Department employees will be on-site often in addition to the project inspector. Please contact us at (330) 854-2044 if you need any immediate assistance during regular work hours.

 